Artifact: Critical-Path Recovery Options — Aurora

Aurora Checkout Redesign -- critical-path recovery -- exercises co-04, co-01.

Situation: 3.1 (checkout end-to-end test suite), on the critical path, runs three days longer than planned. The 17-day critical path is now tracking three days late against the fixed November 15 date.

  • Crashing (spends cost): add a second QA engineer, at contractor day rate, to close out 3.1's remaining test cases in parallel. Recovers time by paying for it directly; does not change the risk profile of the work itself.
  • Fast-tracking (spends risk): start 3.2's environment setup and initial load-test ramp in parallel with 3.1's final regression pass, instead of strictly waiting for 3.1 to finish first. Recovers time by overlapping normally sequential work; accepts the risk that the load test begins against a not-yet-fully-validated build.

Decision: a blended recovery. Fast-track two of the three needed days (overlap 3.2's setup and initial ramp with 3.1's tail end); crash the remaining one day (add a second QA engineer for one day to close out 3.1's last test cases faster). This recovers all three days without moving the fixed November 15 date or cutting scope.