Artifact: Risk Register — Checkout Redesign

Aurora Checkout Redesign -- risk register -- exercises co-10.

#RiskLikelihood (1-5)Impact (1-5)ScoreMitigationOwner
1Apple Pay API introduces a breaking change before launch3412Pin the SDK version, subscribe to Apple's developer changelog, smoke-test weekly against the sandbox.Dinar (payments lead)
2Load test reveals checkout cannot sustain 3x peak traffic3515Run the load test three weeks before launch (not launch week), reserve autoscaling headroom, keep a feature-flag kill switch to the old checkout.Priya (SRE)
3Bayu, the only engineer who knows the legacy cart-persistence code, is on scheduled leave during Sprint 25315Pair a full walkthrough session before leave starts, document cart-persistence quirks in a runbook.Bayu (tech lead)
4Holiday code-freeze policy shortens the usable schedule by one week4312Confirm the exact freeze date with release management now, and build the week into the schedule buffer rather than discovering it late.Dinar
5Finance requests a sixth payment provider mid-project (scope creep)339Route any such request through the change-management decision process rather than silently absorbing it.PM (Aurora)